Rasnick v. Tubbs
126 Ohio App.3d 431, 710 N.E.2d 750 (Ohio
Ct.App. 1998)
PARTIES: Dennis Tubbs (Denny’s Street
Shop)—Appellant
Charles and
Tonyua Rasnick (Bennett & Sieg Auto Wrecking d.b.a. The Rasnick Family
Racing Team)—Appellee.
RELIEF
REQUESTED: Tubbs appeals
an award of damages for $15,903.68.
FACTS: The
parties entered into an oral contract for the construction of a race car in
December of 1994. The Rasnicks were to
supply Tubbs with the engine, transmission, and clutch assembly, not to mention
a 1952 Sports Coupe that was to be turned into a 1952 Chevy Pro Modified Race
Car.
AGREED PURCHASE
PRICE: $52,820 – Parts purchased by Rasnicks would be deducted.
The car was to
be completed over 20 weeks time and the Rasnicks agreed to pay $1,000 each week
for labor. On May 12, 1995 the car was
not completed so the parties found a need for a written contract. The written contract said the same thing
except that the car must be completed within six weeks of receiving the wheels
and the tires. When the vehicle was
finished, the Rasnicks would pay the remainder due in one lump sum.
The tires were
delivered on May 26, 1995 and after the six weeks had passed, the car was still
not completed. The Rasnicks continued
to make payments and on February 26, 1996 they had paid $49,619.25 for a car
that was still not finished. The
Rasnicks called a meeting and Tubbs told them he needed an additional $20,000
to complete the car. With Tubbs
permission, the Rasnicks removed the car from Tubbs’ shop and took it to another
mechanic for completion. (Tubbs denied
these allegations and said he could complete the car for $5,609.70)
ISSUE: Did
the trial court use the correct measure of damages?
HOLDING:
Trial court was wrong because they 1) failed to consider costs other
than labor and 2) it is unclear how the trial court concluded that the vehicle
could be completed for the price the parties bargained for. Judgment affirmed in part, vacated in part
and cause remanded.
REASONING: The
appellate court uses the measure of damages suggested by the Restatement for
compensating an expectation interest.
R2K 347. The loss in value is
the difference between the value of performance rendered without a breach and
the value of performance as it was actually rendered.
DON’T FORGET
WHAT THIS CASE REPRESENTS: “As a lawyer, you need to be creative and to
be informed by your client as to how he or she can be best compensated within
the law. The Rasnick v. Tubbs case is
one that cries out for creative thought, given the lack of a market to assess
the value of the contract”. (cited from the contracts case book).